07

InEnTec Chemical Midland Facility

midplant

Artist's rendering of the plant already under construction.  It is scheduled to be fully operational in late 2009.

Dow Corning signed a long-term contract with InEnTec Chemical to convert chlorinated organic residuals into aqueous hydrogen chloride (HCl) and clean synthesis gas, a replacement for natural gas used to produce steam. The products will then be reused by Dow Corning in its Midland operations. The plant is expected to produce more than 10 million pounds per year of HCl and 11 million BTU's per hour of syngas.

 

Midland_26_March_resized

Actual plant on March 26th, 2009.


April_8

April 8th, 2009


PEM_1_arrives_via_truck

PEM #1 arrives via truck late April.


PEM_1_in_place_web

PEM #1 set in place April 28th, 2009.

UPDATE June 9th, 2009: All major vessels are except for the HCl production system are in place and the structure is essentailly complete.  Final electrical, control and piping installation continues along with refractory installation inside the PEM and TRC.  The project remains on schedule.

UPDATE August 5th, 2009: The HCl production system arrives and is installed.  All major components in place.  Commissioning of various subsystems begin.

SGL_Plant_off_loadSGL_Plant

Aqueous HCl production unit arrives and is set in place.


SGL_Plant_installed

HCl production unit installed.

UPDATE September 3rd, 2009: Commissionings of major vessels and subsystems are nearing completion.  The entire system is expected to be brought up to operating temperatures this week.

O2_Plant_and_boiler

Boiler building (left) and oxygen production plant (4 tanks in back) looking north from TRC platform.